Option Appraisal and Funding agreement for heating systems and decarbonisation measures at Carterton Leisure Centre
16/02/2023 - Option Appraisal and Funding agreement for heating systems and decarbonisation measures at Carterton Leisure Centre
To accept the Salix grant offer and proceed with proposals to decarbonise Carterton Leisure centre with a Heat Pump system and Solar PV. Mitigating some identified project risks by:
(i) introducing project gateways, where a decision will be made to proceed to capital spend at the following stages:-
acceptable contract variation agreed with GLL and,
completion of the Investment Grade Proposal, providing greater confidence in the modelled data around system performance, energy usage and potential savings from PV and battery storage;,
(ii) maximising opportunities to reduce operating costs through energy purchasing agreements, Building Energy Management Systems and the installation of carport PV and battery storage where these options present a sound business case for investment.