Skip to main content

Issue - decisions

Carterton Leisure Centre Decarbonisation

16/09/2024 - Carterton Leisure Centre Decarbonisation

Councillor Andrew Prosser, Executive Member for Climate Action and Nature Recovery, introduced the report, which reviewed opportunities to apply for funding and deliver the decarbonisation of Carterton Leisure Centre.

 

Councillor Andrew Prosser proposed that the Executive agree the recommendations as listed on the original report. This was seconded by Councillor Lidia Arciszewska, was put to a vote, and was unanimously agreed by the Executive.

 

The Executive Resolved to:

  1. Note the review of costs contained within this report and proceed with the preparation of a business case for solar PV and battery storage at Carterton Leisure Centre;
  2. Agree that an application for Public Sector Decarbonisation Scheme or other grant funding should be made with the agreement of the Director of Finance, if grant terms are subsequently published which provide funding which would mean the Council would not have an ongoing revenue deficit.